Διακοπή ρεύματος και επαναφορά

PRINT BEFORE USE!
Material may not be available during shutdown process.

Updated 27/09/2023

Διακοπή ρεύματος

Poweroff:

Επίπεδο 1

Unmount backup filesystem
  1. uranus: umount /mnt
  2. gaia: umount /mnt
EMC VNXe3100, 10.1.2.9

Poweroff procedure (+WAIT, UNPLUG!)

Shut down the system

The shutdown process can take between 25 to 45 minutes to complete.
During this time, the connection to the system will be lost and
you will not have access to Unisphere or the online help.

1. From Unisphere, select Settings > Service System.
2. Enter the Service password to access the Service System page.
3. Under Service Actions, select Shut Down System.
4. Click Execute service action to shut down the
   storage processors (SPs).
5. In the Service Confirmation dialog box, click OK.
6. Check the status of the shutdown process by looking at the
   SP LED indicators:

On VNXe3100 and VNXe3150 systems, the shutdown process is complete
when only the Storage Processor Power LEDs are blinking and all
other Storage Processor LEDs are off.

7. If you are relocating hardware, disconnect cables in the
   following order:

Disconnect the power cables from disk-processor enclosure (DPE)
to power down the SPs.
Disconnect the power cable from the DAEs to power them down.
HP DL145G2
  1. Close control units poweroff
  2. titan (old printserver, “shutdown -p now”), iLO 10.1.2.12
  3. csforum, iLO 10.1.2.30
  4. aeolus, iLO 10.1.2.150
  5. glaucus, iLO 10.1.2.29
  6. unmount /usr/home/{students,staff,grads} from scylla
Εργαστήρια
3D printers
HP DL380G6 esxi5, 10.1.2.205, iLO 10.1.2.105
  1. alumni (alumni-vlan74)
  2. dl380ws*
HP DL380G6 esxi2, 10.7.4.6, iLO 10.1.2.102
  1. titan-printserver (new printserver, titan-new, 10.7.4.44)
  2. mysql-server (dbserver)
  3. calliope-www (cse www, calliope-vlan74)
HP DL380G6 esxi3, 10.7.4.7, iLO 10.1.2.103
HP DL380G7 esxi4, 10.7.4.125, iLO 10.1.2.104
Dell R630 #1 (UP), 10.1.2.40, iLO 10.1.2.110

Επίπεδο 2

Dell R630 #1 (UP), 10.1.2.40, iLO 10.1.2.110
Dell R630 #2 (DOWN), 10.1.2.41, iLO 10.1.2.111

Επίπεδο 3

HP DL145G2
  1. scylla (“shutdown -p now”), iLO 10.1.2.45
  2. rescue, iLO 10.1.2.49
HP DL380G7 esxi4, 10.7.4.125, iLO 10.1.2.104
  1. gatepc73
  2. gatepc74
  3. gatepc76
  4. clonezilla SE (drbl)
  5. charybdis
ESXi(s)
Power cables
  1. Unplug all machines
  2. Turn off, unplug 2x online UPSs
  3. Turn off, unplug 1x rescue UPS (in rack)
  4. Unplug Cisco switch
  5. Unplug HP switch
  6. Unplug mgmt switch
  7. Unplug ATEN KVM
personal machines

Επαναφορά ρεύματος

Poweron

Επίπεδο 1

Power on
  1. ATEN KVM
  2. Cisco switch
  3. HP switch
  4. mgmt switch
  5. 2x online UPSs
  6. 1x rescue UPS
EMC VNXe3100, 10.1.2.9
Power up the system (20+ minutes! Check www!)

To power up a system that is fully powered down:
1. Reconnect the power cables to each DAE in the following exact order:
DAE 0
DAE 1
DAE 2
Power up any remaining DAEs in ascending order.

The green Power Status LED powerlines.gif on each DAE turns on.
For more information on the LEDs, see System LED displays.
2. Reconnect the power cables to each SP in exactly this order:
SP A
SP B

The green Power Status LED on each SP turns on.
HP DL380G7 esxi4, 10.7.4.125, iLO 10.1.2.104
  1. gatepc73
  2. gatepc74
  3. gatepc76
  4. clonezilla SE
HP DL145G2
  1. titan (old printserver), iLO 10.1.2.12
  2. csforum, iLO 10.1.2.30
  3. aeolus, iLO 10.1.2.150
  4. glaucus, iLO 10.1.2.29
  5. scylla, iLO 10.1.2.45
  6. rescue, iLO 10.1.2.49

Επίπεδο 2

Dell R630 #2 (DOWN), 10.1.2.41, iLO 10.1.2.111
Dell R630 #1 (UP), 10.1.2.40, iLO 10.1.2.110

Επίπεδο 3

HP DL380G6 esxi2, 10.7.4.6, iLO 10.1.2.102
  1. calliope-www (cse www)
  2. titan-printserver (new printserver)
  3. mysql-server (NOT!)
HP DL380G6 esxi3, 10.7.4.7, iLO 10.1.2.103
HP DL380G7 esxi4, 10.7.4.125, iLO 10.1.2.104
  1. engineering www (jupiter)
  2. charybdis (NOT!)
Dell R630 #1 (UP), 10.1.2.40, iLO 10.1.2.110
scylla mounts
HP DL380G6 esxi5, 10.1.2.205, iLO 10.1.2.105
  1. alumni (www)
  2. dl380ws*
3D printers
Close control units